Gas data access in Missouri
- Data access rule
- Commission rule
“Utility means, for purposes of this rule, an electrical corporation, gas corporation, heating company, water corporation, or sewer corporation as defined in section 386.020, RSMo” 20 CSR 4240-10.175(1)(D) [source]
- Citation
- 20 CSR 4240-10.175 Customer Information of Electrical Corporations, Gas Corporations, Heating Companies, Water Corporations, and Sewer Corporations
- Green Button required
- Not stated
- Automatic sharing (Connect My Data) required
- Not stated
- Customer can authorize a third party
- Yes
“Specific customer information shall be made available to affiliated or unaffiliated entities only upon consent of the customer or as otherwise provided by law or commission rules or orders.” 20 CSR 4240-10.175(2)(A) [source]
- Gas smart meter opt-out
- Allowed, with a fee
“This rule applies to residential utility service provided by all electrical corporations, gas corporations, sewer corporations, and water corporations as those terms are defined in section 386.020, RSMo.” 20 CSR 4240-10.035(1) [source]
- Opt-out fees
- 20 CSR 4240-10.035 applies to residential service of gas corporations: each utility files an opt-out tariff that may include a one-time all-inclusive fee up to $125 to remove an advanced/hub meter and install a traditional meter and a monthly meter use fee up to $15 (one per meter), plus interest up to 5% on unpaid amounts from unreported or inaccurate self-reads; statutory opt-out right (RSMo 386.820) from 2026-07-01. Spire Missouri (East and West) web page: opt-out at any time; after the initial standard meter installation, one-time $100 meter set-up charge plus $15/month (effective 2025-10-24). Spire's post-rule tariff sheet and Ameren Missouri gas / Liberty / Summit terms not read.
“A one- (1-) time all-inclusive fee, not to exceed one hundred twenty-five dollars ($125), for removal of an advanced or hub meter and to provide and install a traditional meter; A monthly meter use fee, not to exceed fifteen dollars ($15), for the use of a traditional meter.” 20 CSR 4240-10.035(3)(A)1-2 [source]
“if you opt-out after the initial standard meter installation, you will be charged a one-time meter set-up charge of $100 as well as a $15 (effective Oct. 24, 2025) monthly charge” Spire Energy meter upgrade page (Missouri) [source]
- Effective
- 2025-05-30
“Original rule filed Sept. 25, 2024, effective May 30, 2025.” 20 CSR 4240-10.175 history note [source]
- Source
- [source]
The electric row was none_found for data access; 20 CSR 4240-10.175 (original rule filed 2024-09-25, eff. 2025-05-30) names gas corporations and applies equally to electric: specific customer information goes to affiliated or unaffiliated entities only on customer consent (opt-in on a Commission-approved form or recorded verbal consent), aggregated data (4/50 residential screen) on request, reasonable charges allowed, customer information remains the customer's property, each utility files a customer data privacy policy. It is a privacy/consent rule, not a Green Button or interval-data delivery mandate. Scope: Commission-regulated gas corporations (Spire Missouri, Ameren Missouri gas, Liberty, Summit Natural Gas); munis not covered. Opt-out rule 20 CSR 4240-10.035 effective 2026-04-30; annual opt-out reports from 2027-07-01.