Utility Brain

Electricity data access in District of Columbia

Data access rule
Commission order
“the Commission DIRECTS the Potomac Electric Power Company to provide a feasibility report for implementing Green Button Connect My Data in the District within 90 days” Order No. 20364, FC 1130, para. 94 [source]
Citation
Order No. 20364 (June 5, 2020), paras. 16 and 94
Docket
Formal Case No. 1130 (MEDSIS / PowerPath DC)
Green Button required
Not stated
Automatic sharing (Connect My Data) required
Not stated
Customer can authorize a third party
Not stated
Utilities must allow device pairing
Not stated
Smart meter opt-out
Not allowed
“denied a request from the Office of People's Counsel to reconsider an earlier decision that rejected calls to require Pepco to let customers opt out of its AMI program (summary)” Public Utilities Fortnightly, June 1, 2013 (secondary) [source]
Effective
2020-06-05
“FORMAL CASE NO. 1130 ... Order No. 20364 ... June 5, 2020” Order No. 20364 [source]
Source
[source, unverified]

Pepco is the only electric distribution utility. Order No. 20364 directed Pepco only to file a Green Button Connect My Data feasibility report within 90 days (and to consider GBC for residential customers), not to implement it; later FC 1130 workgroup on GBCMD implementation reconvened 2021 (no implementing order found). Opt-out: per a 2013 trade-press report the PSC rejected OPC requests to require a Pepco AMI opt-out and denied reconsideration; no later order found (order number not located).

What District of Columbia utilities offer

UtilityIntervalGreen ButtonPair a deviceSDR-readable
Potomac Electric Power CoHourlyDownload My DataNot statedNo